JUDUL : MEMBUAT APLIKASI PENJUALAN
Tahap-Tahap
Pelaksanaannya :
1 bulan = 4 minggu × 6 hari = 24 hari efektif.
1 bulan = 4 minggu × 6 hari = 24 hari efektif.
1. Optimistic Duration (OD) = 2 bulan × 24 hari = 48 hari.
2. Pessimistic Duration (PD) = 4 bulan × 24 hari = 96 hari.
3. Expected Duration (ED) = 2 bulan × 24 hari = 48 hari.
D
= (1×OD) + (4×ED) + (1×PD)
6
D
= (1×48 hari) + (4×48 hari) + (1×96 hari)
6
D
= 48 + 192 + 96
6
D
= 336
6
D
= 56