Kamis, 02 Juni 2016

REKAYASA PERANGKAT LUNAK


JUDUL : MEMBUAT APLIKASI PENJUALAN 

Tahap-Tahap Pelaksanaannya :  

1 bulan = 4 minggu × 6 hari = 24 hari efektif.
1.      Optimistic Duration (OD) = 2 bulan × 24 hari = 48 hari.
2.      Pessimistic Duration (PD) = 4 bulan × 24 hari = 96 hari.
3.      Expected Duration (ED) = 2 bulan × 24 hari = 48 hari.

D = (1×OD) + (4×ED) + (1×PD)
6
D = (1×48 hari) + (4×48 hari) + (1×96 hari)
                                    6
D = 48 + 192 + 96
               6
D = 336
         6
D = 56